The IRN is the document that lets equipment leave the vendor. It is short, and every line matters.
An IRN releases the equipment for shipment against the inspection scope. It does not replace the purchaser’s final acceptance on site, and it does not cover what was outside the ITP.
Check that every hold point is closed, that conditional items are listed with an owner and a date, and that the data book is complete or has an agreed submission date.