5 blocking points we often see at FAT

Field notes from recent factory acceptance tests. None of these is technical in the strict sense; all of them cost days.

1. Test sheets that do not match the approved procedure

The vendor fills in sheets from an older revision. Check the IFC revision of the procedure before the test starts, not during the report.

2. Instruments without valid calibration

A gauge out of calibration invalidates the test. Ask for calibration certificates with the test notification.

3. Test conditions that differ from site conditions

Example seen on a davit FAT: a 50 Hz test supply for 60 Hz equipment. Agree in advance what is tested, how, and what will be re-verified on site.

4. Missing traceability

A lifting point without a traceable safe working load, a part without its heat number: the test may pass, but the equipment cannot be released.

5. Documentation not ready at the release date

Certificates, NDT reports and painting reports arrive after the test. Review them progressively, not in the last week.