Field notes from recent factory acceptance tests. None of these is technical in the strict sense; all of them cost days.
The vendor fills in sheets from an older revision. Check the IFC revision of the procedure before the test starts, not during the report.
A gauge out of calibration invalidates the test. Ask for calibration certificates with the test notification.
Example seen on a davit FAT: a 50 Hz test supply for 60 Hz equipment. Agree in advance what is tested, how, and what will be re-verified on site.
A lifting point without a traceable safe working load, a part without its heat number: the test may pass, but the equipment cannot be released.
Certificates, NDT reports and painting reports arrive after the test. Review them progressively, not in the last week.